Lalin railway connects the municipalities of Lhasa and Nyingchi. This project initiated in June 2015, and will become the third operational way in Tibet. Due to terrains, high altitudes, and other geographic complications of up to 3500m (11,500ft), this railway project is widely considered as a milestone and miracle in the worldwide railway construction history.
This project remains one of Ougan’s proudest accomplishments, for introducing static and pile load test in areas that were not able to otherwise. This proves our attitude to strive for the best, and take on projects that others seem incapable of.
During 2015 and 2016, a total of 21 piles were tested by China National Institute of Architecture Engineering Quality Inspection utilizing Ougan Technology’s patented Super-cell technology.
Single pile testing load: 25,000kN/40,000kN (5,620kip/8,992kip)
Pile diameter: 1.25m/1.5m (49.2in/59.0in)