Upturn the multiple type Super Cell and put it on even ground. In the meantime, hydraulic hose, connectors of grout pipe, rod extensometers etc. on the other side should be protected.
Pour concrete into the upward cone-shape flow-guiding mechanism and then the downward one;when pouring concrete into the upward cone-shape flow-guiding mechanism, pour the hydraulic hose from the small hole at the side of the cone-shape flow-guiding mechanism.
Pour concrete into cone-shape flow-guiding mechanism, and tamp with vibrating spear thoroughly – to ensure the concrete is more stiff than the pile shaft’s stiffness.
Cell should be left for the concrete to dry for at least 10 hours. Do not move the cell in the meantime.
When concrete of the upward cone-shape flow-guiding mechanism freeze,flipping the cone-shape flow-guiding mechanism with crane and then pour concrete into the downward cone-shape flow-guiding mechanism.
Ougan Super Cells make the bi-directional static load test easy, accurate, and affordable!